Rosie-O-Gradys_Getting-Ready-To-Install-Second-Floor-Metal-Deck-Project-RosO1-101

Project RosO1-101
from our portfolio of Recent Projects

Our Recent-Projects Include New Construction As-Well-As Addition and Renovation of House, Commercial, Condo, Light-Industrial, Multi-Family Buildings, ...

Rosie O'Grady's Restaurant & Pub on 23 Mile Road in Chesterfield Twp Michigan -- Building Addition and Upgrading

Yes Siree, in my post Rosie-O-Gradys_Second-Floor-Joists-Installation-Part3-Project-RosO1-101, I showed you that the Second Floor joist installation was nearing completion.

Dave Dotson and crew will be making sure that every joist has the required number of fasteners properly installed and that the joists are ready for installation of metal deck for the concrete floor.

So, the guys are getting ready for installation of metal deck.

I have presented here for your reference a few job site pictures -- I will keep you posted with work progress as we go along.



Rosie-O-Gradys_Getting-Ready-To-Install-Second-Floor-Metal-Deck-Project-RosO1-101 ... Picture 1

Rosie-O-Gradys_Getting-Ready-To-Install-Second-Floor-Metal-Deck-Project-RosO1-101-Picture-1


ANAND Enterprises Project RosO1-101





Rosie-O-Gradys_Getting-Ready-To-Install-Second-Floor-Metal-Deck-Project-RosO1-101 ... Picture 2

Rosie-O-Gradys_Getting-Ready-To-Install-Second-Floor-Metal-Deck-Project-RosO1-101-Picture-2


ANAND Enterprises Project RosO1-101



Rosie-O-Gradys_Getting-Ready-To-Install-Second-Floor-Metal-Deck-Project-RosO1-101 ... Picture 3

Rosie-O-Gradys_Getting-Ready-To-Install-Second-Floor-Metal-Deck-Project-RosO1-101-Picture-3


ANAND Enterprises Project RosO1-101



Rosie-O-Gradys_Getting-Ready-To-Install-Second-Floor-Metal-Deck-Project-RosO1-101 ... Picture 4

Rosie-O-Gradys_Getting-Ready-To-Install-Second-Floor-Metal-Deck-Project-RosO1-101-Picture-4


ANAND Enterprises Project RosO1-101



Rosie-O-Gradys_Getting-Ready-To-Install-Second-Floor-Metal-Deck-Project-RosO1-101 ... Picture 5

Rosie-O-Gradys_Getting-Ready-To-Install-Second-Floor-Metal-Deck-Project-RosO1-101-Picture-5


ANAND Enterprises Project RosO1-101



Rosie-O-Gradys_Getting-Ready-To-Install-Second-Floor-Metal-Deck-Project-RosO1-101 ... Picture 6

Rosie-O-Gradys_Getting-Ready-To-Install-Second-Floor-Metal-Deck-Project-RosO1-101-Picture-6


ANAND Enterprises Project RosO1-101



Rosie-O-Gradys_Getting-Ready-To-Install-Second-Floor-Metal-Deck-Project-RosO1-101 ... Picture 7

Rosie-O-Gradys_Getting-Ready-To-Install-Second-Floor-Metal-Deck-Project-RosO1-101-Picture-7


ANAND Enterprises Project RosO1-101



beginning of Rosie-O-Gradys_Getting-Ready-To-Install-Second-Floor-Metal-Deck-Project-RosO1-101

back to our Energy Efficient Building Network home page

Fill in the following form to subscribe to our upcoming news letter, to keep
up with our latest updates, and to tell us how we can help with your Dream Home building project:

Please note that all fields followed by an asterisk must be filled in.
Name
E-mail Address*
question or comment



Partner With Us

If you are involved with energy efficient building projects as:
  • Designer
  • Architect
  • Engineer
  • Contractor
  • Specialty contractor
  • Surveyor
  • Developer
  • Supplier
  • Financier
  • ....
we invite you to tell us about yourself by filling in the special contact form
I have setup for your convenience. Let us see if we can create synergy
by utilizing our combined resources and create a win-win situation!






Yours Sincerely


Yogi Anand, D.Eng, P.E.

Energy Efficient Building Network LLC
308 Longford Dr -- Rochester Hills MI 48309 U.S.A.
Phone: +1-248-375-5710; Cell: +1-248-766-1546